Construction project delivery in Nigeria is characterised by persistent time and cost overruns that undermine infrastructure investment and the provision of public services. This study examines project performance in Ondo State, Nigeria, through archival analysis of 52 completed construction projects and a questionnaire survey of 29 construction professionals, and proposes a targeted Digital Intervention Framework (DIF) for the five highest-ranked efficiency constraints. A quantitative mixed-method design was adopted: archival records yielded descriptive performance statistics, while the Relative Importance Index (RII) and Relative Significance Index (RSI) were computed. Findings reveal severe delivery underperformance: 72.97% of building projects and 93.33% of road projects exceeded their contract duration, with mean time overruns of 20.81% and 26.00% respectively; 75% of building projects and all road projects exceeded their contract cost, with mean cost overruns of 12.78% and 19.33% respectively. The five highestranked efficiency constraints are adequate planning (RII = 3.975), number of reworks (RII = 3.828), payment delays (RII = 3.586), cost control systems (RII = 3.483), and information coordination (RII = 3.414). These findings are limited to Ondo State, which constrains direct generalisation; however, the sample comprises experienced multidisciplinary practitioners whose cross-professional perspective strengthens the credibility of the factor rankings. The DIF proposed in this paper maps each of the five priority efficiency factors to specific digital tools appropriate to the infrastructure and capacity context of Nigerian small construction firms, offering practical guidance for construction clients, contractors, consultants, and policymakers seeking to reduce project overruns through digital transformation.
Keywords: Construction project performance; time overrun; cost overrun; digitalisation; Nigeria; Ondo State; digital project management.